This page collects all information on the general BD upgrade of the existing GSI facility.
… as usual: under construction…
Todo list from first meeting with CSCO on “Agenda 2017” (11 May 2015): todo list
Starting in Feb. 2016 a sequence of bi-weekly project meetings has been set up in order to organize and prepare for the required upgrade of diagnostic devices.
The working title of the project is for time being: BIDUCOR (Beam Instrumentation Data acquisition Upgrade and COntrol system Retrofit).
Participants: HR, BWH, AR, PK, TG, TH, OC, MSchw
presentation slides with comments
It was agreed to schedule the next meeting in 2 weeks, to proceed with the brain storming about SIS18 components.
As a next step HEST components will be treated as well.