+ | === DAQ Upgrade: === | ||
+ | |||
+ | With the construction of the new FCC (FAIR Control Center) all DAQ systems installed in the Main Control Room (" | ||
+ | |||
+ | UNIMON needs a full renovation in soft- and hardware. In addition the complete DAQ system, for the time being installed in the HKR-consoles, | ||
+ | |||
+ | === Status: === | ||
+ | |||
+ | * ADC firmware ready | ||
+ | * Adapterbox production in progress | ||
+ | * GUI available | ||
+ | * So far no further requirements from operations defined | ||
+ | |||
+ | === Open Issues: === | ||
+ | |||
+ | * No future installation rack in LSB 4 defined. | ||
+ | * Movement of all Coax cables has a potential risk for damages | ||
+ | * Unclear, if and how to archive data. Unimon is a dedicated online monitoring system so far. | ||
+ | * No WR Timing in Main Control Room | ||
+ | | ||
===== Electronics ===== | ===== Electronics ===== | ||
Line 16: | Line 36: | ||
The gateware sources can be found in the following git repository: | The gateware sources can be found in the following git repository: | ||
- | [[https:// | + | [[https:// |
The corresponding documentation can be found here: | The corresponding documentation can be found here: | ||
- | [[ds: | + | [[ds: |
- | The same documentation can be found here as a PDF: {{: | + | The same documentation can be found here as a PDF: {{: |